The South Burnett Regional Council will spend almost $10 million upgrading the region’s water and sewerage infrastructure this year as part of a 10-year, $90 million replacement program.
Upgrades to the Kingaroy Water Supply system will consume more than 75 per cent of this year’s spend on water supplies, with a $4 million upgrade of Kingaroy’s water treatment plant and $1.5 million spent on replacement of mains, the rising main and reservoirs.
The remaining $1.76 million will be spread across the region’s other seven water supply schemes.
Kingaroy will also consume more than half of this year’s $2.59 million spend on sewerage, with an upgrade to the Kingaroy Sewerage Plant and mains replacements.
But work will also be undertaken at the Nanango and Murgon treatment plants and the Proston treatment lagoons, as well as mains replacements in Blackbutt, Nanango, Wondai and Murgon.
Here’s where the money will be spent:
Water Supply Assets – $7,358,898
Blackbutt Supply Mains Replacements – $100,000
Nanango Supply Replace Pump Bore C & Monitoring – $20,000
Nanango Supply Mains Replacement – $320,000
Kingaroy Supply Rising Main – $800,000
Kingaroy Supply Treatment Plant – $4,050,000
Kingaroy Supply Reservoirs – $50,000
Kingaroy Supply Mains Replacement – $700,000
Wondai Supply Pump Stations – $80,000
Wondai Supply Reservoirs – $100,000
Wondai Supply Mains Replacement – $240,000
Murgon Supply Treatment Plant – $195,000
Murgon Supply Pump Stations – $50,000
Murgon Supply Mains Replacement – $140,000
Proston Supply Treatment Plant – $20,000
Proston Supply Mains Replacement – $70,000
Proston Rural Supply Mains Replacement – $70,000
Wooroolin Supply Bores – $40,000
Telemetry Upgrades – $30,000
Debt Repayments – $283,898
Waste Water (Sewerage) Supply Assets – $2,589,370
Blackbutt Mains & Manhole Replacements – $120,000
Nanango Treatment Plant – $20,000
Nanango Mains & Manhole Replacements – $300,000
Kingaroy Treatment Plant Upgrade – $650,000
Kingaroy River Road trunk main replacement – $600,000
Kingaroy Mains & Manhole Replacements – $200,000
Wondai Mains & Manhole Replacements – $250,000
Murgon Treatment Plant (Intake Screen) – $80,000
Murgon Mains & Manhole Replacements – $270,000
Proston Treatment Lagoons (upgrade for sludge removal) – $20,000